Sl No Name Type Installed Capacity (MW)
1 Likhimro HEP Hydro 24
2 Lang HEP Hydro 1
3 Tehok mHP Hydro 1
4 Duilumroi mHP Hydro 0.540

Central Sector

Sl No Name Type Installed Capacity (MW) State Share
1 Kopili-I Hydro 200 6.17%
2 Kopili-II Hydro 25 5.76%
3 Khadong Hydro 50 6.68%
4 Panyor (Ranganadi) Hydro 405 5.36%
5 Doyang Hydro 75 17.99%
6 Pare Hydro 110 5.43%
7 Kameng Hydro 600 1.50%
8 Loktak Hydro 105 6.46%
9 Assam Gas Based Power Plant Thermal (Gas) 291 5.83%
10 Agartala Gas Turbine Combine Cycle Power Plant Thermal (Gas) 135 5.40%
11 Bongaigaon Thermal Power Plant Thermal (Coal) 750 4.96%
12 Farakka Super Thermal Power Plant Thermal (Coal) 1600 0.43%
13 Kahalgaon Super Thermal Power Plant Thermal (Coal) 840 0.42%
14 Talcher Super Thermal Power Plant Thermal (Coal) 1000 0.42%
15 Palatana OTPC Thermal (Gas) 726.6 7.16%

Private Sector

Sl No Name Type Installed Capacity (MW)
1 Hydro-Private 1 Hydro 4.5